Environmental Remediation > Fuel Oil Recovery
U.S. Government Institution
SES
was awarded a contract to install a remediation system
at a U.S. Government institution located in Fort Wayne,
Indiana. The remediation system included bio-venting and
total fluids recovery.
The project was initiated with the installation of
recovery wells in accordance with project
specifications. Conveyance lines from recovery wells to
the remediation equipment building were then installed
using horizontal boring methods. SES Environmental
designed and installed a remediation system capable of
attaining the project-specified performance objectives.
Final system testing was then conducted, and a notice of
substantial completion was received.
The project is currently in the operation and
maintenance phase. SES is currently performing routine
groundwater sampling, reporting, and system maintenance
in accordance with contract requirements.
|