|
Environmental Consulting >
Underground Petroleum Storage Tank Management
City of Fort Wayne, Indiana
SES Environmental was awarded a contract by the
City of Fort Wayne to serve as the designated
consultant/engineer for municipal underground
storage tank issues. The city owned and operated 43
underground storage tanks at 21 municipal sites. The
sites included fire stations, utility facilities,
and several abandoned properties.
SES Environmental initiated work by conducting a
compliance audit to determine the regulatory status
of each tank. This work was followed by a
preliminary investigation to determine environmental
conditions at each tank area. Information from this
work indicated most sites were impacted by petroleum
fuel compounds; however, the impact extent was
generally confined to surrounding soil. Shallow
groundwater impact was only present at three tank
sites.
SES Environmental worked closely with various
city department supervisors to prepare
specifications and a bidding package for tank
removals. During the removal process, SES documented
site activities and performed closure assessments in
accordance with regulatory guidance.
SES Environmental utilized the preliminary
investigation data to design a corrective action
plan for addressing petroleum impacted soil at each
site. The plan specified the construction of four
centrally-located treatment cells to receive
contaminated soil from each tank area. The treatment
cells were constructed using membrane liners, and a
leachate collection system. Approximately 2,500
cubic yards of petroleum-contaminated soil were
treated. The centralized treatment cell plan allowed
for attaining immediate clean closure at 18 of the
21 tank sites, and also avoided the cost and
liability of landfill disposal.
After removing the tanks, and implementing
corrective actions, SES processed and secured cost
reimbursement for environmental expenditures through
the Indiana Excess Liability Trust Fund.
Community School System
SES
Environmental provided the Fort Wayne Community
School System with engineering design services
required to meet the 1998 UST upgrade requirements.
In order to comply with these requirements, the
school system was required to close tanks, upgrade
piping, and install new tanks.
Project work was initiated by conducting a
compliance audit to determine the specific measures
to be implemented at each tank site. SES then
prepared project work specifications, material
specifications, and construction drawings for each
tank upgrade site. Upon receiving approval from FWCS
to proceed with the project, SES Environmental
prepared all necessary bidding documents, reviewed
bids, and provided engineering oversight during
construction. The project was successfully
completed, and in compliance with the 1998 tank
upgrade deadline.
|