|
Environmental Consulting >
Comprehensive Environmental Site Management
Commercial 40-Acre Shopping Center Complex
An initial Phase I ESA conducted at a large
shopping center complex (40 acres) indicated the
presence of 16 underground petroleum storage tanks.
Thirteen of the tanks were used to store fuel oil
for individual heating systems utilized by the
shopping center tenants. Three of the tanks were
associated with a former service station, which
occupied a portion of the site.
The project was initiated by removing the 13 fuel
oil tanks. SES Environmental completed closure
assessments for each tank area. Contaminated soil
encountered at ten tank locations was placed into a
treatment cell, which was constructed behind the
shopping center complex. Clean closure was attained
at each fuel oil tank area.
Evidence of a significant gasoline release was
observed at the former service station tank area.
Source impacted soil was removed and placed into a
separate treatment cell. A subsequent Phase II
investigation indicated the presence of aqueous and
free-phase petroleum contamination. A remediation
system was designed, fabricated and installed by
SES. The system recovered 740 gallons of gasoline
product over a period of 18 months, and lowered
product levels in the monitor wells from 3.5 feet to
less than 1/8". Final residual product was recovered
using a program consisting of routine extraction via
a mobile, liquid-ring vacuum pump. Aqueous-phase
petroleum compounds were addressed through
remediation by natural attenuation.
The initial Phase I ESA also indicated a former
dry-cleaning operation was present at the shopping
center complex. A Phase II investigation in this
area of the site revealed the presence of PCE
impacted soil and groundwater. The investigation
included both lateral and vertical contaminant
delineation. Investigation results were used to
support a comprehensive risk assessment that
included an exposure pathway assessment, soil to
groundwater leaching models, and groundwater
contaminant fate and transport modeling. The
remedial action plan developed for this area of the
site consisted of soil vapor extraction to remove
PCE from the vadose zone, and plume stability
monitoring.
Automotive Parts Manufacturer
SES Environmental provided environmental
consulting and field services required for a
pre-acquisition investigation at a large metal
tooling facility. Investigation was conducted at
former USTs, ASTs, metal-plating areas, and on-site
buried waste disposal areas. A background assessment
was also conducted to characterize site-specific
geologic and hydrogeologic conditions, and to also
determine background constituent concentrations for
comparison to results obtained from several of the
investigation areas.
The Phase II investigation was followed by
focused remedial efforts at specific areas of the
site, including two hazardous waste management
units, and several on-site waste disposal areas.
Impacted soil in these areas was removed and
transported off-site for disposal. Site work was
completed under budget, and within an expedited time
schedule.
|